Proposed Project Management System for PT. GTU: A Case Study of Piping System Construction Project

  • Muhammad Rival Abizar Sekolah Bisnis dan Manajemen, ITB, Bandung, Indonesia
  • Gatot Yudoko Sekolah Bisnis dan Manajemen, ITB, Bandung, Indonesia
Keywords: EPC, PMBOK, Project Failure, Project Management System, Change Control

Abstract

Engineering, procurement and construction (EPC) projects place a single contractor in charge of design, materials and construction under tight time and cost targets. In Indonesia many projects also rely on subcontractor labor and owner supplied materials, which increases coordination risk. PT GTU experienced a failure on a piping project for a paper mill in Riau, known as BM4. This thesis examines why the project moved away from its plan and what kind of project management system could have reduced the likelihood of failure. BM4 is analysed as a single case. The study assumes that complex projects usually fail because of an accumulation of management choices rather than one event. It aims to identify the key factors behind the failure using the six project constraints as a frame, to explain how they affected schedule, site readiness, subcontractors and cash flow, and to develop a project management system tailored to GTU. A qualitative design is used. Data comes from semi structured interviews with seven internal stakeholders and from supporting project documents. The material is coded by project constraints, analyzed using Current Reality Trees to link visible symptoms to root causes, and compared with selected PMBOK Guide Sixth Edition processes as a benchmark for expected practice. The results indicate three main root causes: lack of project leadership and discipline, absence of formal change control and unrealistic schedule and resource baselines. Together they explain the difficulties in BM4, including unstable subcontractor manpower, coordination problems and repeated quality issues. The thesis concludes by proposing a practical project management system for GTU that clarifies governance routines, introduces an integrated change control procedure and strengthens rules for setting and updating baselines to support future EPC projects.

Downloads

Download data is not yet available.

References

Ahmad, T., Firdaus, A. H., Abdulah, R., & Firlana, A. M. (2023). Peran sektor rancang bangun industri (EPC) dalam mewujudkan transisi energi dan dampaknya bagi makro ekonomi (Policy Brief No. 6/2023). INDEF.

Althoey, F., Houda, M., Waqar, A., & Nisar, S. (2024). Comprehensive framework for Integrated Construction Platforms (ICP) implementation and its effect on project success. Ain Shams Engineering Journal, 15, 103152. https://doi.org/10.1016/j.asej.2024.103152

Alzubi, K. M., Alaloul, W. S., Malkawi, A. B., Al Salaheen, M., Qureshi, A. H., & Musarat, M. A. (2023). Automated monitoring technologies and construction productivity enhancement: Building projects case. Ain Shams Engineering Journal, 14, 102042. https://doi.org/10.1016/j.asej.2022.102042

Badan Pusat Statistik (BPS). (2024a). Statistik Konstruksi 2023 / Construction Statistics 2023 (Vol. 43). BPS–Statistics Indonesia.

Badan Pusat Statistik (BPS). (2024b). Construction in Figures 2024. BPS–Statistics Indonesia.

Coccia, M. (2023). Causes of failures in project management: Analysis and inductive evidence. Qeios. http://dx.doi.org/10.32388/8SGX71

CRIF Indonesia. (2023, January 18). The projection of construction in Indonesia in 2023 and challenges in the post-pandemic era. CRIF Indonesia.

Giri, U., Aggrawal, A., & Pandey, S. (2020). Why projects fail. International Journal of Current Engineering and Technology, 10(1), 40–45. https://doi.org/10.14741/ijcet/v.10.1.7

Isbahi, M. B., Zuana, M. M. M., & Toha, M. (2024). The Multi-Social Relation of the Cattle Industry in the Plaosan Subdistrict Animal Market of Magetan Regency. Malacca: Journal of Management and Business Development , 1(1), 31–46. https://doi.org/10.69965/malacca.v1i1.51

Khairullah, T. M., Al-Akraise, S. A., & Naseer, A. (2022). Identification of the main causes of risks in engineering procurement construction projects. Journal of the Mechanical Behavior of Materials, 31, 282–289. https://doi.org/10.1515/jmbm-2022-0029

Nurdiana, A., & Susanti, R. (2020). Assessing risk on the Engineering Procurement Construction (EPC) project from the perspective of the owner: A case study. IOP Conference Series: Earth and Environmental Science, 506, 012040. https://doi.org/10.1088/1755-1315/506/1/012040

Project Management Institute (PMI). (2013). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (5th ed.). PMI.

Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). PMI.

Sarwani, S., Baihaqi, I., & Utomo, C. (2024). Causes of delay in EPC projects: The case of Indonesia. International Journal on Advanced Science, Engineering and Information Technology, 14(2), 618–628.

Shabbir, R., Naveed, S., & Cheema, S. M. (2023). Evaluation of the factors behind the failure of project management practices. Journal of Development and Social Sciences, 4(3), 490–501. https://doi.org/10.47205/jdss.2023(4-III)47

Tamin, P., Perwitasari, D., & Tamin, R. (2015). Subcontracting management in an EPC project: A case study of delay risks. Proceedings of International Structural Engineering and Construction, 2. https://doi.org/10.14455/ISEC.res.2015.13

Published
2026-03-10
How to Cite
Abizar, M. R., & Yudoko, G. (2026). Proposed Project Management System for PT. GTU: A Case Study of Piping System Construction Project. Indonesian Interdisciplinary Journal of Sharia Economics (IIJSE), 9(1), 7920-7938. https://doi.org/10.31538/iijse.v9i1.9138